| Electric |
| Electric on site? Provider? |
Yes, Tucson Electric Power |
| Line size |
3 Phase |
| Capacity |
13.8KVA (2.8 MVA) available to each superpad. 138kV also available with improvements, Prince 10 is actively pursuing the construction of a 100 MVA substation dedicated to the project. Please contact David Couture (TEP) Business Development Manager: dcouture@tep.com. |
| Distance to substation |
1 Mile |
| Is substation serving other sites? |
Yes |
| Cost (per kWh) |
https://www.tep.com/business-rates/ |
| Any rate increases expected? |
No |
| Any upgrades needed to existing infrastructure? |
No |
| Any additional costs? |
No |
| Natural Gas |
| Natural gas line on site? Provider? |
Yes, Southwest Gas |
| Line size |
Four-inch and Six-inch |
| Capacity |
TBD, Please contact Carlos Del Valle, CEM. Southwest Gas, Industrial Gas Engineer, Key Accounts 520-794-6425 carlos.delvalle@swgas.com |
| Cost (per SCF) |
Business Services (swgas.com) |
| Any rate increases expected? |
No |
| Location of closest distribution/transmission line |
On site |
| Any upgrades needed to existing infrastructure? |
No |
| Any additional costs? |
No |
| Water |
| Water line on site? Provider? |
Yes, Tucson Water |
| Line Size |
12-in. and 16-in. |
| Capacity |
2,500 gals per minute |
| Cost (per 1,000 gallons) |
$7.39 (base & surcharges combined); Also, $96.06 flat rate per month for a 2-inch meter |
| Water source |
Groundwater |
| Any rate increases expected? |
No |
| Any upgrades needed to existing infrastructure? |
No |
| Any additional costs? |
No |
| Wastewater |
| Waste Water line on site? Provider? |
Yes, Pima County Wastewater Reclamation Dept. |
| Line Size |
10-inch and 72-inch |
| Discharge limits |
376,153 gals/day Prince 10 North. No Limit Prince 10 South |
| Name of waste water treatment facility |
Tres Rios |
| Capacity of waste water treatment facility |
30,000,000 gals/day |
| Discharge cost (per 1,000 gallons) |
Multifamily or Regular Commercial: $4.70 per 1,000 gal. Industrial (e.g., Electric Component Mfgr.): $5.36/1,000 gal. |
| Other place(s) discharge could if treated on site? |
No |
| Any rate increases expected? |
No |
| Any upgrades needed to existing infrastructure? |
No |
| Any additional costs? |
No |
| Broadband/Telecommunications |
| Service Provider |
First Digital, Century Link & Verizon |
| Please describe infrastructure on site |
Fiber Optic |
| Any rate increases expected? |
No |
| Any upgrades needed to existing infrastructure? |
No |
| Any additional costs? |
No |